Analysis of the project success factor through time, cost, labour, health, safety, environment and quality aspects at PT XYZ

Authors

  • Moh Komarudin Universitas Mercubuana
  • Rosalendro Eddy Nugroho Universitas Mercubuana

DOI:

https://doi.org/10.4995/ijpme.2022.16021

Keywords:

Success Project Factor, Schedule Performance, Cost Performance, Safety Performance, Productivity Coefficient, Client Satisfaction

Abstract

This study aims to analyze the failure factors of PT. XYZ in 2018 – 2020 in terms of time, cost, labor, Health, Safety, and Environment (HSE), and quality based on the Success Project Factor (SPF). It includes 183 projects with the Non-Probability Sampling technique. The researcher uses fishbone and Pareto to identify problems. The results showed Schedule Performance Index (SPI)"‰<"Š1 indicated the project is in the late category, the Cost Performance Index (CPI)"‰<"‰1 indicated cost overrun, Safety Performance Index (SFPI)"‰>"‰0 indicated the K3 target could not be reached, the Client Satisfaction Index (CSI)"‰="‰34.03, indicated that it is in the dissatisfied category, then Productivity Coefficient Plan < Realization, it meant the workforce was less productive. After the analysis of fishbone and Pareto, the data show that the highest cause was 13% due to lack of supervision, project cost aspects were 13% due to delays, HSE project aspect were 13% due to no K3 process before work begins, the quality aspect was 17% due to no training, and the labor aspect was 17% due to poor worker discipline.

Downloads

Download data is not yet available.

Author Biographies

Moh Komarudin, Universitas Mercubuana

Economics and Business Faculty

Rosalendro Eddy Nugroho, Universitas Mercubuana

Business Managemet Post Graduate Program

References

Arianie, G. P., & Puspitasari, N. B. (2017). Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi Dan Efektifitas Sumber Daya Perusahaan (Studi Kasus: Qiscus Pte Ltd). Jurnal Teknik Industri, 12(3), 189-196. https://doi.org/10.14710/jati.12.3.189-196

Ayano, E., & Teshome, W. (2018). Factors Contributing for Delay in Government Construction Projects in Oromia, Ethiopia. The International Journal of Business & Management, 6(1), 131-146.

Dharsika, I. G. E., Budiartha, I. N., & Yansen, I. W. (2017). Analisis Kualitas Manajer Proyek Terhadap Pelaksanaan Proyek Konstruksi (Studi Kasus: Di Denpasar dan Badung). Jurnal Spektran, 5(1). https://doi.org/10.24843/SPEKTRAN.2017.v05.i01.p02

Dharma, A. A. B., Putera, I. G. A. A., & Parami, A. A. D. (2017). Manajemen Risiko Keselamatan Dan Kesehatan Kerja (K3) Pada Proyek Pembangunan Jambuluwuk Hotel & Resort. Jurnal Spektran 5(1), 1-87. https://doi.org/10.24843/SPEKTRAN.2017.v05.i01.p06

Frefer, Mahmoud, Haleema, & Almamlook. (2018). Overview Success Criteria and Critical Success Factors in Project Management. Industrial Engineering & Management, 07(01). https://doi.org/10.4172/2169-0316.1000244

Ismiyati, I., Sanggawuri, R., & Handajani, M. Penerapan Manajemen Resiko pada Pembangunan Proyek Perpanjangan Dermaga log (Studi Kasus: Pelabuhan DalamTanjung Emas Semarang). Media Komunikasi Teknik Sipil, 25(2), 209-220. https://doi.org/10.14710/mkts.v25i2.19467

Kamau, M. E., Jane, G., & John, K. (2018). Influence of Human Related Factors on Success of Construction Projects in Kenya. The International Journal of Business & Management, 6(5), 251-283.

Kathongo, S. M. (2017). Total Quality Management Practices and Performance of Rural Electricity Distribution Projects in Kenya. The International Journal of Business & Management, 5(3), 66-71.

Kerzner, H. (2010). Project Management - Best Practices - Achieving Global Excellenc 2nd ed. New York: John Wiley & Sons, Inc., Hoboken, New Jersey

Lesmana, I. P. D., & Antika, E. (2019). Manajemen Proyek Dengan Scrum. Absolute Media.

Maidamisa, A. A. (2017). Comparative Analysis of Activity Duration in Project Management. The International Journal of Business & Management, 5(12), 158-162.

Meiliawan, F., & Nugroho, R. E. (2020). Peningkatan Kualitas Pelayanan PT XYZ Sebagai Badan Sertifikasi ISO. Warta Pendidikan / e-Journal, 4(5), 4-10

Messah, Y. A., Sina, D. A., & Manubulu, C. C. (2013). Analisa Indeks Biaya Untuk Pekerjaan Beton Bertulang Dengan Menggunakan Metode Sni 7394-2008 Dan Lapangan (Studi Kasus Pada Proyek Pembangunan Asrama STIKES Chmk Tahap III). Jurnal teknik sipil, 2(1), 49-62.

Miano, K. J. (2017). Managing Stakeholders Diversity in Determining Project Success: A Stakeholders Matrix Approach. The International Journal of Business & Management, 5(9), 1-4.

Ogolla, P. J., Mugambi, F., & Obwongi, J. (2019). Influence of Project Organizational Risk Management Policy on Performance of Mom-basa County Government Projects, Kenya. The International Journal of Business & Management, 7(5). https://doi.org/10.24940/theijbm/2019/v7/i5/BM1905-013

Rochman, F., & Wahyuni, H. C. (2018). Analisa Pengaruh Pengen-dalian Kinerja Proyek Terhadap Mutu Proyek Konstruksi Dengan Menggunakan Uji Statistika. Jurnal Teknik Industri, 12(1), 01-06. https://doi.org/10.14710/jati.12.1.01-06

Septiawan, D. B., & Bekti, R. (2016). Analysis of Project Construction Delay Using Fishbone Diagram at PT Rekayasa Industri. Journal of business and management, 5(5), 634-650.

Sutawijaya, A. H., & Nawangsari, L. C. (2018). The Strategic of Implementation Health and Safety to Improved Performance Construction Management System (Case in Arcamanic project, Indonesia). International Journal of Engineering & Technology, 7(2.29), 176-181. https://doi.org/10.14419/ijet.v7i2.29.13312

Sutawidjaya, A.H., Nawangsari, L.C. & Djamil, M. (2019). Operasi Strategi & Proses Manajemen. Jakarta: Mitra Wacana Media

Wang, X., & Nagahira, A. (2017). The Impact of User Innovation on New Product Development Project Success in Japanese Firms, Comparative Study between B2B and B2C Projects. The Interna-tional Journal of Business & Management, 5(7), 287-297.

Wicaksono, I.Y. (2016). Analisis Kinerja Pekerja Pada Keterlambatan Proses Fabrikasi Pengerjaan Proyek Coal Fired Boiler Milik PT Alstom Power Esi Surabaya. S.T. Skripsi. Fakultas Teknologi Kelautan Institut Teknologi Sepuluh Nopember: Sura-baya.

Yanova, N. (2015). Assessment of satisfaction with the quality of education: customer satisfaction index. Procedia-Social and Behavioral Sciences, 182, 566-573. https://doi.org/10.1016/j.sbspro.2015.04.782

Downloads

Published

2022-01-31

How to Cite

Komarudin, M., & Nugroho, R. E. (2022). Analysis of the project success factor through time, cost, labour, health, safety, environment and quality aspects at PT XYZ. International Journal of Production Management and Engineering, 10(1), 33–50. https://doi.org/10.4995/ijpme.2022.16021

Issue

Section

Papers